171205 | PA17/11083 | Demolish all existing buildings and forecourt structures inc removal of underground fuel tanks and infras
PA17/11083 | Demolish all existing buildings and forecourt structures inc removal of underground fuel tanks and infrastructure. Construct new sales building, forecourt canopy (car & hgv), fuel dispensers, fenced external bin store, ad blue tank, external plant, forecourt pavings. Install underground fuel tanks, new fuel pipework inc vent stack and replacement external floodlighting.
| Shell Oil Uk Ltd Garage 15 Carwin Rise Loggans Hayle Cornwall TR27 5DG
171221 | Extract from FLOOD RISK AND DRAINAGE ASSESSMENT FOR SHELL HAYLE AT CARWIN RISE , HAYLE , CORNWALL
Extract from FLOOD RISK AND DRAINAGE ASSESSMENT FOR SHELL HAYLE AT CARWIN RISE , HAYLE , CORNWALL report
3.0 FLOOD RISK ASSESSMENT
3.1 Assessment Approach
This assessment aims to minimise any impact of the development on flood risk through
adequate consideration of flooding issues and the inclusion of appropriate mitigation.
3.2 Fluvial Flood Risk
The development area, because of its proximity to a main river, is considered to be at
risk of fluvial flooding despite the presence of flood defences in the form of bunds that
have been constructed along both banks of the main river.
The map showing the local main rivers and other watercourses in the area is provided
in Appendix G. read more »